Updating construction progress of SMC Tan Tao factory after 2 weeks of deployment
06/11/2014(26/06/2013) Perspective of the project SMC Steel factory The project SMC Tan Tao Steel factory was started deploying on 16/06/2013. After the first week of construction, completed items include: construction camps installation, daily
(26/06/2013)

Perspective of the project SMC Steel factory
The project SMC Tan Tao Steel factory was started deploying on 16/06/2013. After the first week of construction, completed items include: construction camps installation, daily activity area and WC; establishing power and water system for construction site; erecting temporary fencing, temporary roads to enter construction site; ground levelling; foundation pits excavation; foundation liner concrete.
By the end of the second week, it has basically finished camps erection, temporary fence, materials warehouse, finishing foundation formwork and reinforcement; foundation concrete (100 foundation pits); machine bed foundations excavation, excavation and concrete foundation liner (100 foundation pits next).
Some photos at construction site
Acceptance testingbeforethe foundation concrete
Concreting workshop foundation
Installing formwork and rainforement for the foundation pits
Excavation foundation bed of cutting machines
Excavation and concrete foundation liner of the workshop
Panorama of the work site
- Duy Hoang -
Tin công ty
-
EUROFINS GHI NHẬN NĂNG LỰC TỔNG THẦU DESIGN & BUILD CỦA CJSC
Eurofins ghi nhận năng lực tổng thầu Design & Build của...
-
CJSC ĐỘNG THỔ DỰ ÁN NHÀ MÁY GLITTER VIỆT NAM – CÔNG TRÌNH TIÊN PHONG TẠI KCN HẢI LONG, HƯNG YÊN
Ngày 06/12, Lễ động thổ Dự án Nhà máy Glitter Việt Nam đã...
-
CJSC ĐƯỢC COOLER MASTER VINH DANH NHÀ CUNG CẤP DỊCH VỤ XUẤT SẮC 2025
Ngày 24/10/2025, tại thành phố Huệ Châu (Trung Quốc), Tập...