Update construction schedule of SMC Tan Tao project
06/11/2014(27/08/2013) Photos at the construction site: Disassembly Larsen bracing system-3m, hole depth is -6m Check formwork, reinforce of tank wall at second stage, hole depth is -6m Cast concrete for tank wall at the second stage, hole depth is
(27/08/2013)
Photos at the construction site:
Disassembly Larsen bracing system-3m, hole depth is -6m
Check formwork, reinforce of tank wall at second stage, hole depth is -6m
Cast concrete for tank wall at the second stage, hole depth is -6m
Check technical box of cutting machine foundation
Check technical box of cutting machine foundation
Cast concrete at elevation ±0.000 of cutting machine foundation
Clean, check defect list (cutting machine foundation)
Kerb sewer, build septic tank for rain water drainage
Install reinforce, formwork of semi – axis foundation at axis 14 (J-C)
Defects list
Plaster mortar for second coat of underground tank
Install floor steel for the base (3-7),( F-J) 24.08.2013
The over view of SMC Tan Tao project
- Duy Hoang -
Tin công ty
-
EUROFINS GHI NHẬN NĂNG LỰC TỔNG THẦU DESIGN & BUILD CỦA CJSC
Eurofins ghi nhận năng lực tổng thầu Design & Build của...
-
CJSC ĐỘNG THỔ DỰ ÁN NHÀ MÁY GLITTER VIỆT NAM – CÔNG TRÌNH TIÊN PHONG TẠI KCN HẢI LONG, HƯNG YÊN
Ngày 06/12, Lễ động thổ Dự án Nhà máy Glitter Việt Nam đã...
-
CJSC ĐƯỢC COOLER MASTER VINH DANH NHÀ CUNG CẤP DỊCH VỤ XUẤT SẮC 2025
Ngày 24/10/2025, tại thành phố Huệ Châu (Trung Quốc), Tập...