NUTRICARE – UPDATE SCHEDULE CONSTRUCTION SCHEDULE ON AUGUST 2016.

08/09/2016

At the end of August 2016, the project "Nutricare milk factory" continues being implemented with urgency and continuity 24 / 24h with the target of handing over the project to the Owner at committed time. Details as follows: - The office


 

At the end of August 2016, the project "Nutricare milk factory" continues being implemented with urgency and continuity 24 / 24h with the target of handing over the project to the Owner at committed time. Details as follows:

- The office building was on the stage of building exterior walls at 2 floor, erecting scaffolding, formwork, roof beams.

- workshop is erecting structural steel frame.

- Despite many obstacles from rainy weather, the ultility and infrastructure  are still concentrated on construction  CJSC drastically

 

Here are the latest images which we update at the site of "Nutricare milk factory" project in August 2016.

Project perspective

 

Erection of steel structure at workshop 

 

Rebar and formwork for foundation bracing at ultility

 

Cover and compact stone base for workshop foundation

 

Contact Us

A: Room 605, Toyota My Dinh Building, No. 15 Pham Hung Street, Cau Giay Ward, Hanoi.

T: (+84) 243.7957.717

F: (+84-4).3795.7716

The South branch:No. 55, S Street, Lakeview City Urban Area, Binh Trung Ward, Ho Chi Minh City.

Tel: (+84-28) 35 35 1497

E: cjsc@cjsc.vn

Hotline: (+84) 983.384.888

© CJSC. All rights reserved | Design by Vtechcom

Lên đầu trang