BEAR RESCUE CENTRE – UPDATE SCHEDULE OF 6-DAY CONSTRUCTION
11/09/2016In the end of 2014, CJSC completed and handed over the project "Bear Rescue Centre" in Tam Dao National Park to Asia Animals Organization. The center provide homes for 200-250 bears in the past few years. With the demand for expanding
In the end of 2014, CJSC completed and handed over the project "Bear Rescue Centre" in Tam Dao National Park to Asia Animals Organization. The center provide homes for 200-250 bears in the past few years. With the demand for expanding houses for Bears, the investor continue trusting and assigning CJSC to construct Bear house number 9&10 and semi-wild area on the last day of August 2016. Project construction period is 181 days. CJSC arranged human resource to start preparation work in September 3rd, 2016. Hereby are some images of construction site since 6- day commence
Project perspective

Inspection of rebar, formwork for F1, F2 foundation at axis A,B (from 1 to 10)

Inspection of rebar, formwork for F1, F2 foundation at axis C,D (from 1 to 10)

Checking slump of foundation concrete

Foundation work
Luong Trinh
Company News
-
CJSC – A Strategic Partner for Chinese Investors in Vietnam
On June 14, 2025, in Hanoi, CJSC participated in the...
-
GROUNDBREAKING CEREMONY OF VINACOREMAX VIETNAM FACTORY PROJECT - PHASE I On June 6, 2024, CJSC held the Groundbreaking Ceremony of...
-
CJSC AFFIRMS OUR POSITION AS ONE OF VIETNAM'S TOP 10 CONTRACTORS IN 2024
On the evening of May 31, 2024, at the BCI Asia Awards held...