CNF – UPDATE CONSTRUCTION SCHEDULE ON AUGUST 2016

07/09/2016

Move on the first days of the 6th months since construction, overcome difficulties of stormy days, under close instruction of Board of Directors, Management Board of construction site, indirect and all direct employee have attempted to


 Move on the first days of the 6th months since construction, overcome difficulties of stormy days, under close instruction of Board of Directors, Management Board of construction site, indirect and all direct employee have attempted to ensure construction schedule of “CNF animal feed factory”.

Project is entering the completion stage, detail as below:

- Factory finished erecting steel structure, installing metal sheet and now is installing lighting system

- The office building was handed over to the Owner 2 months ago.

- Civil, road, landscape is being completed by CJSC

 

Hereby are some images of project construction

 

Perspective of project

 

 

 

Manufacturing tower is under completion 

 

Office building was finished and handed over to the Owner

 

 

 

 

 

Covering base for road 

 

Complete the weight station and workshop 

 

Finish company name board  

 

Contact Us

A: Room 605, Toyota My Dinh Building, No. 15 Pham Hung Street, Cau Giay Ward, Hanoi.

T: (+84) 243.7957.717

F: (+84-4).3795.7716

The South branch:No. 55, S Street, Lakeview City Urban Area, Binh Trung Ward, Ho Chi Minh City.

Tel: (+84-28) 35 35 1497

E: cjsc@cjsc.vn

Hotline: (+84) 983.384.888

© CJSC. All rights reserved | Design by Vtechcom

Lên đầu trang