CNF site in June 6th , 2016

06/06/2016

Hung Yen, January 6th 2016 Currently, CNF animal feed factory is implementing the working items: Finishing office building, canteen, parking house, erecting steel structure of manufacturing tower, erecting steel structure for wall and


Hung Yen, January 6th 2016

 

Currently, CNF animal feed factory is implementing the working items: Finishing office building, canteen, parking house, erecting steel structure of manufacturing tower, erecting steel structure for wall and roof and finishing foundation and bracing in workshop 2; now we are under rolling and compacting slab of workshop 1 and workshop 2. All CJSC’s staff are highly concentrating on  implementing work and overcoming the extremely hot weather. CJSC still ensure project quality and procedure of quality control at CNF animal feed factory. Here are some images at the site:

Perspective

Office building is under being plastered and finished

Building canteen

Erecting manufacturing tower

Material warehouse

Leveling and rolling at workshop 2

Workshop 1 has finished erecting steel structure of wall, roof, and now is under rolling and compacting slab

 

Author: Nguyen Huy Quynh

Liên hệ

Trụ sở chính:

P.605 Toà nhà TOYOTA Mỹ Đình, 15 Phạm Hùng, Nam Từ Liêm, Hà Nội.

Tel: (+84) 243.7957.717

Fax: (+84-4).3795.7716

Chi nhánh phía Nam:

Số nhà 55, đường S, khu đô thị Lakeview City, phường An Phú, thành phố Thủ Đức, Tp. HCM

Tel: (+84-28).3535.1497

Email: cjsc@cjsc.vn
Hotline: (+84) 983.384.888

© CJSC. All rights reserved | Design by Vtechcom

Lên đầu trang