CJSC CARRIED OUT A INSPECTION OF IPC FACTORY
14/01/2019On December 5th, 2018, an internal inspection was taken place at the construction site of the "STEEL PROCESSING AND MECHANICAL PRODUCTS FACTORY - IPC" in Minh Duc commune - My Hao district - Hung Yen province before it was handed over to owner. CJSC's delegation was led by Mr. Tran Van Bien - Head of Construction Department and Mr. Vi Van Thuong - Head of Safety.
On the side of construction site, there was the participation of Mr. Nguyen Huu Tuyen - Project Director, Mr. Dao Van Thoai - the site manager and a large number of engineers.
After Mr. Nguyen Huu Tuyen made a report on the progress of the project, the delegation organized a factory tour to take over the quality of each construction item.
Every work items is carefully inspected by the delegation through their assessments, measures and improvements in order to apply to the next project.
Mr. Tran Van Bien gave compliments to engineers who had many initiatives and many methods which help complete project on schedule with high quality. Besides, he also pointed out some small errors so that the Site Management Board can promptly repair before the official handover date to the investor.
Even though all items have been completed before November 30 to hand over to the investor, CJSC still focuses on this internal inspection as a summarizing activity to help the construction engineers and departments review works for future improvement.
Here are some pictures from the inspection:
Company News
-
GROUNDBREAKING CEREMONY OF VINACOREMAX VIETNAM FACTORY PROJECT - PHASE I On June 6, 2024, CJSC held the Groundbreaking Ceremony of...
-
CJSC AFFIRMS OUR POSITION AS ONE OF VIETNAM'S TOP 10 CONTRACTORS IN 2024 On the evening of May 31, 2024, at the BCI Asia Awards held...
-
TOP 3 GLOBAL ELECTRONICS ENTERPRISE BREAKS GROUND ON A NEW FACTORY IN VIETNAM Recently, CJSC hosted the groundbreaking ceremony for Phase...