03/04/2019In the end of 2014, CJSC completed and handed over the project "Bear Rescue Centre" in Tam Dao National Park to Asia Animals Organization. The center provide homes for 200-250 bears in the past few years. With the demand for expanding
In the end of 2014, CJSC completed and handed over the project "Bear Rescue Centre" in Tam Dao National Park to Asia Animals Organization. The center provide homes for 200-250 bears in the past few years. With the demand for expanding houses for Bears, the investor continue trusting and assigning CJSC to construct Bear house number 9&10 and semi-wild area on the last day of August 2016. Project construction period is 181 days. CJSC arranged human resource to start preparation work in September 3rd, 2016. Hereby are some images of construction site since 6- day commence
Project perspective
Inspection of rebar, formwork for F1, F2 foundation at axis A,B (from 1 to 10)
Inspection of rebar, formwork for F1, F2 foundation at axis C,D (from 1 to 10)
Checking slump of foundation concrete
Foundation work
Luong Trinh
Tin công ty
- ẤM ÁP NGHĨA CỬ SẺ CHIA VỚI ĐỒNG BÀO BỊ THIỆT HẠI DO CƠN BÃO SỐ 3 GÂY RA Tính đến ngày 17/9, bão số 3 gây mưa lũ, sạt lở, ngập lụt...
- CJSC CHUNG TAY HỖ TRỢ CHÍNH QUYỀN ĐỊA PHƯƠNG ĐẮP ĐÊ PHÒNG CHỐNG LŨ LỤT Ngày 11/09/2024, BCH Dự án Nhà máy MCC Việt Nam cùng KCN...
- CJSC KÍNH MỪNG ĐẠI LỄ VU LAN BÁO HIẾU 2024 Lễ Vu Lan không đơn thuần chỉ có ý nghĩa tôn giáo thiêng...