Start erecting steel structure in EXT site
(01/03/2014) Photos at the construction site of EXT Vietnam factory – Bac Giang Building office walls The front and back of the office CJSC’s workers are erecting steel structures. Steel structures of the workshop Overview of EXT
See more
Latest photos of Ohashi construction site - Vinh Phuc
(03/03/2014) The newest photos of Ohashi Vietnam Factory. All construction works are mostly finished, ready for handing over to the investor for production operation. Factory signboard Outside the workshop Rooms inside the office General
See more
Progress of Vietnam Bear Rescue Center update (03/2014)
(12/03/2014) Some photos of executed items at Vietnam Bear Rescue Center: Master perspective of Vietnam Bear Rescue Center Item Bear Houses 5&6 Inspection of reinforcement and formwork of house columns Concreting house columns Floor
See more
Steel structure installation for EXT works site
(12/03/2014) Perspective of EXT Engineering Vietnam factory Photos at the site Inspecting purlins of workshop and office. Picture of installing purlins for workshop walls Installation of roof purlins Installing electric pipe for the
See more
Formal acceptance and handover of the project Ohashi Vietnam Factory
(15/03/2014) The project Ohashi Vietnam Factory is invested by Ohashi Tekko Vietnam, INC and located in Binh Xuyen II IZ – Vinh Phuc province with the total investment capital of $ 14,346 Mil. This project aims to manufacture spare parts
See more
Update construction progress of EXT project
(25/03/2014) Photos of EXT works by 21/03/2014 Metal roofing work The investor are inspecting works Plastering walls inside the office Checking work items carefully Inside the workshop, look from the office - Duy Hoang -
See more
Finish metal roofing installation at EXT works site
(05/04/2014) Some photos of metal roofing and another work at EXT construction site – Bac Giang province The overview from the outside of the factory Complete metal wall panels installation Installing metal frame for plaster ceiling in the
See more
Pictures of the finishing work in EXT construction site
(18/04/2014) EXT Engineer Vietnam factory is a project of Japanese investor and is deploying in Dong Vang Industrial complex. The project aims to produce metal processing production. After 4 months of construction, the project is now in
See more
Photos of Vietnam Bear Rescue Center – Tam Dao, Vinh Phuc
(19/04/2014) Pictures of conducted items Bear Houses 7&8 Photo of Bear Houses 5&6 Antifouling painting for steel columns of surrounding fence - Duy Hoang -
See more
EXT Vietnam Factory – Accelerate to finish and hand over
(08/05/2014) EXT metal processing factory has being deployed by CJSC contractor in the early of 2014 at Dong Vang Industrial Complex – Bac Giang province. Up to now, after 4 months of construction, the project is in the last stages of
See more
Hope Zone works – CJSC accelerates construction schedule of concrete and road base
(09/05/2014) Some pictures at construction site Spread out and compact base layer the product warehouse The plan of material warehouse Internal roads Concreting foundation M20 Sewer system installation Construction plan - Duy Hoang -
See moreGround breaking ceremony of HNJ Vietnam factory (phase II)
(10/05/2014) In the morning of October 05th, 2014, Construction application and transfer of tachnologies joint stock company held the ground breaking ceremony of HNJ Vietnam exporting leather clothes (Phase II) Perspetive of HNJ Vietnam
See moreCompany News
-
CJSC – A Strategic Partner for Chinese Investors in Vietnam
On June 14, 2025, in Hanoi, CJSC participated in the...
-
GROUNDBREAKING CEREMONY OF VINACOREMAX VIETNAM FACTORY PROJECT - PHASE I On June 6, 2024, CJSC held the Groundbreaking Ceremony of...
-